DBFL Consulting Engineers (DBFL) were commissioned by Dún Laoghaire-Rathdown County Council & the NTA to undertake a review of the existing Taney Cross junction layout in Dundrum, including adjoining junctions and approaches, and to propose measures to improve operational efficiency and safety at this key node.

 

The scheme comprised of detailed site audits to identify problems associated with the current configuration for all road users and significant traffic modelling.

 

A PARAMICs S Model was constructed of the existing Taney Cross Junction to simulate the existing operational traffic conditions. A future model was also produced to assess the impact of proposed junction alterations. The visual outputs from the models were used to present findings to local representatives as well as the client and the NTA.

 

The PARAMICs model was supplemented by TRANSYT modelling to determine the optimum traffic signal staging plan to be implemented.

More Projects

Dublin Office

☎ +353 1 400 4000

✉ info@dbfl.ie

 

Ormond House
Upper Ormond Quay
Dublin 7
D07 W704

 

 

Galway Office

☎ +353 91 33 55 99

✉ info@dbfl.ie

 

Odeon House
7 Eyre Square
Galway
H91 YNC8

 

 

 

 

Cork Office

☎ +353 21 202 4538

✉ info@dbfl.ie

 

14 South Mall
Cork
T12 CT91

 

Waterford Office

☎ +353 51 30 95 00

✉ info@dbfl.ie

 

Suite 8b The Atrium
Maritana Gate, Canada St
Waterford
X91 W028